- This topic has 7 replies, 4 voices, and was last updated 13 years, 8 months ago by .
-
Topic
-
On July 1, Year 1, Gee, Inc. leased a delivery truck from Marr Corp. under a 3-year operating lease. Total rent for the term of the lease will be $36,000, payable as follows:
12 months at $500 = $6,000
12 months at $750 = $9000
12 months at $1,1750 = $21,000
All pmts were made when due. In Marr’s June 30, year 3, B/S, the accrued rent receivable should be reported as:
A. $0
B. $9,000
C. $12,000
D. $21,000
Correct answer is $9,000 and I understand why that is. However, if the question asked was “What’s the rent receivable at June 30, Year 3,” then would the answer have been $21,000?
Since this question asks ACCRUED rent receivable, $9000 is correct. BUT total rent receivable should be $21,000, correct?
Just curious. Thanks:)
- The topic ‘Quick FAR question’ is closed to new replies.
