- This topic has 3 replies, 3 voices, and was last updated 13 years, 6 months ago by .
-
Topic
-
I just don’t get this.
during 2009, m corp started a construction job with a total contract price of 600k. the job was completed 12/15/10. additional data are as follows:
actual costs incurred 2009: 225,000 2010: 255,000
estimated remaining costs 2009: 255,000 2010: blank
billed to customer 2009: 240,000 2010: 360,000
received from customer 2009: 200,000 2010: 400,000
under the completed contract method, what amount should m recognized as gross profit for 2010?
BEC: Done
REG: Done
AUD: Done
FAR: DoneI'M DONE!!!!!! AAAAAAAAAAAAAAAAAAAAAAHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHHH!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
Viewing 3 replies - 1 through 3 (of 3 total)
Viewing 3 replies - 1 through 3 (of 3 total)
- The topic ‘FAR question.. PLEASE HELP!!!’ is closed to new replies.
