FAR – Percentage-of-Completion Question Help!

  • Creator
    Topic
  • #1675961
    xpa17
    Participant

    Hi ninjas,

    Here again with another confusing %-of-completion questions. 🙂

    Q1: Mill Construction Co. uses the percentage-of- completion method of accounting. During Year 1, Mill contracted to build an apartment complex for Drew for $20,000,000. Mill estimated that total costs would amount to $16,000,000 over the period of construction. In connection with this contract, Mill incurred $2,000,000 of construction costs during Year 1. Mill billed and collected $3,000,000 from Drew in Year 1. What amount should Mill recognize as gross profit for Year 1?”

    The answer is $250,000 because of the following:
    Total contract sales price = $20,000,000
    Less total estimated cost of contract = $16,000,000
    Total Gross Profit = $4,000,000
    Cost incurred to date/total est. cost of contract = $2,000,000/$16,000,000 = 1/8
    Gross profit recognized in YR 1 = $4,000,000 * 1/8 = $500,000

    Q2: Haft Construction Co. has consistently used the percentage-of-completion method. On January 10, Year 1, Haft began work on a $3,000,000 construction contract. At the inception date, the estimated cost of construction was $2,250,000. The following data relate to the progress of the contract:
    Income recognized at 12/31/Year 1 = $ 300,000
    Costs incurred 1/10/ Year 1 through 12/31/Year 2 = $1,800,000
    Estimated cost to complete at 12/31/Year 2 = $600,000
    In its income statement for the year ended December 31, Year 2, what amount of gross profit should Haft report?

    The answer is $150,000 because:
    Contract price = $3,000,000
    Total cost = $2,400,000 (1,800,000 + 600,000)
    Expected gross profit 600,000
    Cost incurred to date/total est. cost of contract = (18/24) = 75%
    Profit to date $450,000
    Profit previously recognized (300,000)
    Year 2 profit $ 150,000

    ———–> Why is Q1’s total cost not $18,000,000 like the way we did in Q2? I read the similar posts in the forum, but I am still confused of exactly when to combine the cost of estimated cost and actual incurred cost.

    Any help is greatly appreciated!!

Viewing 1 replies (of 1 total)
  • Author
    Replies
  • #1675967
    Anonymous
    Inactive

    Q1 shows actual cost incurred. There is no mention of changes in the total cost. Q2 says that the total cost changed because it shows cost incurred + the estimated cost to complete is more than initially planned.

    Hope this helps.

Viewing 1 replies (of 1 total)
  • The topic ‘FAR – Percentage-of-Completion Question Help!’ is closed to new replies.