- This topic has 2 replies, 2 voices, and was last updated 9 years, 5 months ago by .
-
Topic
-
I posted two questions from Becker below this. How come one question uses actual overhead of 100,000 hours to come up with the budgeted overhead. and another question uses the actual 94,000 to come up with the budgeted overhead.
I knwo my question might be confusing so i put an arrow to the two numbers im talking about
>Water Control, Inc. manufactures water pumps and uses a standard cost system. The standard factory overhead costs per water pump are based on direct labor hours and are shown below:
Variable overhead (4 hours at $8/hour) $ 32
Fixed overhead (4 hours at $5*/hour) 20
Total overhead cost per unit $ 52*Based on a capacity of 100,000 direct labor hours per month.
The following additional information is available for the month of November.22,000 pumps were produced although 25,000 had been scheduled for production.
94,000 direct labor hours were worked at a total cost of $940,000.
The standard direct labor rate is $9 per hour.
The standard direct labor time per unit is four hours.
Variable overhead costs were $740,000.
Fixed overhead costs were $540,000.
The fixed overhead spending variance for November was:a.
$240,000 unfavorable.
b.
$70,000 unfavorable.
c.
$15,000 favorable.
d.
$40,000 unfavorable.Actual fixed overhead $ 540,000
Budgeted fixed overhead (
>100,000 DL hrs. × $5/hr.) 500,000
Unfavorable variance $ 40,000question 2
Water Control, Inc. manufactures water pumps and uses a standard cost system. The standard factory overhead costs per water pump are based on direct labor hours and are shown below:
Variable overhead (4 hours at $8/hour) $ 32
Fixed overhead (4 hours at $5*/hour) 20
Total overhead cost per unit $ 52
*Based on a capacity of 100,000 direct labor hours per month.The following additional information is available for the month of November.
22,000 pumps were produced although 25,000 had been scheduled for production.94,000 direct labor hours were worked at a total cost of $940,000.
The standard direct labor rate is $9 per hour.
The standard direct labor time per unit is four hours.
Variable overhead costs were $740,000.
Fixed overhead costs were $540,000
.
The variable overhead spending variance for November was:
a.
$24,000 favorable.
b.
$96,000 favorable.
c.
$12,000 favorable.
d.
$60,000 favorable.
ExplanationBudgeted variable overhead (
>94,000 DL hrs. × $8/hr.) $ 752,000
Actual variable overhead 740,000
Favorable variance $ 12,000
- The topic ‘BEC Becker question that i dont understand’ is closed to new replies.