Question regarding preventive cost from CPA released questions

  • Creator
    Topic
  • #177479
    Anonymous
    Inactive

    As part of a benchmarking process, a company’s costs of quality for the current month have been

    identified as follows:

    Employee training $20,000

    Product recalls 8,000

    Scrap 4,500

    Quality inspectors 48,000

    Preventive maintenance 19,500

    Supplier education expense 17,500

    Materials inspection expense 60,000

    Processing product returns 2,500

    What amount is the company’s prevention cost for the current month?

    a. $39,500

    b. $57,000

    c. $165,000

    d. $175,500

    Explanation

    Choice “b” is correct.

    I got the answer wrong, and I am guessing the answer “Employee Training + Preventive Maintenance + Supplier Education Expense”

    My question is why are materials inspection expense & quality inspectors not included, but supplier education expense included in preventive cost?

Viewing 3 replies - 1 through 3 (of 3 total)
  • Author
    Replies
  • #412161
    Anonymous
    Inactive

    Perhaps because material inspection would only detect problems that had already been purchased it wouldn't prevent them. Same with the quality inspectors.

    #412162
    Anonymous
    Inactive

    Those would be appraisal costs.

    #412163
    k1zuna
    Member

    just spend 5 mins memorizing the list on becker's textbook…

    FAR - Passed
    AUD - Passed
    BEC - Passed
    REG - 8/22/2013

Viewing 3 replies - 1 through 3 (of 3 total)
  • The topic ‘Question regarding preventive cost from CPA released questions’ is closed to new replies.