- This topic has 1 reply, 2 voices, and was last updated 4 years, 7 months ago by .
-
Topic
-
Hi everyone, I’m a little bit confused as to when you should or should not include normal spoilage in EU computations. Is it safe to assume that if the question does not state that “spoiled units are assigned to units completed and transferred” that we should not include spoilage in finished goods?
First question
a company adds material at the beginning of the process in department m. Data concercing the materials used in March production are as follows:
WIP at 3/1 16,000 units
Started during March 34,000 units
Completed and transferred to next department during March 36,000 units
Normal spoilage incurred 4,000 units
WIP at 3/31 10,000
Using weighted-average method, the equivalent units for the materials unit cost calculation are: answer: 46,000
Ok I have no problem solving this question
Finished Goods is 36k
plus WIP end Materials 10k x 100% = 10,000 (ending wip is 16k +34k -36k -4k)
Total equivalent units for materials = 46,000
Now the second question (this is the one that confuses me):
Forming department is the first of two-stage production process. spoilage is identified when the units have completed the forming process. costs of spoiled units are assigned to units completed and transferred to the second department in the period spoilage is identified. the following info concerns the company’s conversion costs in may 2005
WIP 5/1 (50% complete) 2000 units, conversion costs 10,000
units started during may 8000 units, conversion costs 75,500
normal spoilage 500
units completed & transferred 7,000 units
ending work-in-process (80% complete) 2,500
Using the weighted average method, what was the company’s conversion cost transferred to the second production department? answer 67,500
this is how I solved it
Finished Goods is 7,000
plus WIP end Conversion 2,500 x 80% = 2,000 (ending wip is 2k +8k -500 -7k)
Total equivalent units for conversion costs = 9,000
Total conversion costs 85,500 divided by Equivalent units 9,000 = 9.5
conversion cost 7,000 x 9.5 = 66,500. According the answer key this is incorrect because I’m supposed to include the normal spoilage of 500 in Finished goods when calculating the equivalent units. So the correct rate is 85,500/9,500 = 9.0 and the correct conversion cost is 7,500 x 9 = 67,500.
Thanks!
REG 68,67,83(7/2010); FAR 43,71,80(8/2010); AUD 85(11/2010); BEC 74,79(2/2011)
NYS CPA 5/2011
EA 2/2011
- The topic ‘Question on normal spoilage & weighted-average method’ is closed to new replies.