BEC Study Group Q1 2016 - Page 44

Viewing 15 replies - 646 through 660 (of 1,158 total)
  • Author
    Replies
  • #749540
    Anonymous
    Inactive

    Moniker I think that normally that would be the case with spoilage but the q stated that we had to assume that there was no spoilage. I decided to go forward thinking that B is incorrect bc components needed per unit neither decreases or increases.

    #749541
    MaLoTu
    Participant

    Lets just hope that we don't get a weird question like that in the real exam :-/

    #749542
    monikernc
    Participant

    I am so dumb today. Honestly, I feel like I am back to day one on some of these. Serious fatigue has set in. I will just keep plugging away.

    Thanks for your help!

    FAR 7/25/15 76!
    AUD 10/30/15 93
    BEC 2/27/16 82
    REG 5/23/16 88!
    Ninja Book and MCQ and the forum - all the way!!!
    and a little thing i like to call, time and effort!
    if you want things to change, you have to do something different

    #749543
    MaLoTu
    Participant

    Cortes- it says they are at capacity, so in order to produce more they would have to have less output per unit, no? That is now the only way I see the question making sense, lol.

    #749544
    monikernc
    Participant

    Next question. I foolishly extended my exam date without checking my mcq expiration date. Exam is 27. MCQs expire 26th. Should I renew to have access right up to exam and through score release 12 days later? If I have to retake it will be as early in april as I can get a test date. What time of day do they expire?

    FAR 7/25/15 76!
    AUD 10/30/15 93
    BEC 2/27/16 82
    REG 5/23/16 88!
    Ninja Book and MCQ and the forum - all the way!!!
    and a little thing i like to call, time and effort!
    if you want things to change, you have to do something different

    #749545
    Anonymous
    Inactive

    MaLoTu if that were the case then B(or II) would be correct and the answer was that only A (or I) was correct. This is a messed up question BEC “style”. I hope I do not see one like this on the exam.

    #749546
    monikernc
    Participant

    Cortes, I was hoping learning curve would be “easy” points.

    FAR 7/25/15 76!
    AUD 10/30/15 93
    BEC 2/27/16 82
    REG 5/23/16 88!
    Ninja Book and MCQ and the forum - all the way!!!
    and a little thing i like to call, time and effort!
    if you want things to change, you have to do something different

    #749547
    MaLoTu
    Participant

    I was able to reschedule my exam for 2/27… 2 extra days to study!

    #749548
    Moeshow
    Participant

    I have a question, when you guys reschedule your exam do you have to go through any extra hoops to do so or do you just go to prometrics and reschedule from there without any trouble or extra steps being taken?

    BEC 2/26/2016 81
    FAR 05/2016

    Purely Roger CPA Review, for now!

    #749549
    MaLoTu
    Participant

    @moeshow- you reschedule on the prometric site. You need the confirmation they sent you when you first scheduled (it is a long number with six or seven zeros in the first part, at least all mine have been). It is $35 to reschedule within a certain timeframe.

    #749550
    Zyx
    Participant

    SaveBandit; hope this helps..
    volume variance focuses on fixed overhead variance. The way I remember is volume is “used”, so it is the difference between fixed overhead applied and budgeted fixed overhead. So if the applied overhead is less than budgeted then it is unfavorable because the actual production is less than planned (actual used * POR= fixed overhead applied).

    capacity variance is the difference between actual fixed overhead and budgeted fixed overhead. It presents “spent” overhead. So if actual overhead is greater than budgeted then it is unfavorable because spent too much than planned.

    total variance is the difference between actual and standard overhead.

    Did you get that question from Becker? The explanation seems confusing. Ninja explains better that budgeted fixed overhead is given ($20,000). You just have to find applied fixed overhead which is actual 19000 frames*$1/unit. The difference is $1000 unfavorable since produced less than budgeted.

    REG: 77 x2
    BEC: 81 x3
    FAR: 68 retake 10/1
    AUD: 8/27

    #749551
    Zyx
    Participant

    Guys, I have a question about variable costing. Variable selling and admin is not included in variable cost to calculate CM, is it correct?

    REG: 77 x2
    BEC: 81 x3
    FAR: 68 retake 10/1
    AUD: 8/27

    #749552
    Moeshow
    Participant

    Zyx11

    All variable costs are included in CM
    Sales
    Variable expenses
    = CM

    VARIABLE EXPENSES—Meaning all. They are just not included in your COGS, which only include variable manufacturing costs. DM, DL and variable O/h

    BEC 2/26/2016 81
    FAR 05/2016

    Purely Roger CPA Review, for now!

    #749553
    Moeshow
    Participant

    @MaLoTu

    Really? That is it? so no wait time or anything? When I called prometrics they told me I had to do these extra steps and etc, darn. All it took was a reschedule online.

    BEC 2/26/2016 81
    FAR 05/2016

    Purely Roger CPA Review, for now!

    #749554
    Anonymous
    Inactive

    zyx11 we include it to arrive at CM. But note that they are not capitalized (they are expensed) so under variable costing it looks something like this:

    Sales
    – manufacturing (included in inventory) variable cost
    = Manufacturing CM
    – variable selling and adm costs
    = Total CM
    – BOTH manufacturing, selling Fixed Cost
    = Net Income

Viewing 15 replies - 646 through 660 (of 1,158 total)
  • The topic ‘BEC Study Group Q1 2016 - Page 44’ is closed to new replies.