[Q1] BEC Study Group 2014 - Page 22

Viewing 15 replies - 316 through 330 (of 440 total)
  • Author
    Replies
  • #524878
    Anonymous
    Inactive

    Hi everyone. I'm taking BEC again in less than a month and getting pretty overwhelmed with all the formulas. I didn't memorize many the first time I took BEC and I believe that's why I failed. This is too much information to retain.

    #524822
    Anonymous
    Inactive

    Hello everyone. Im taking BEC in a couple of days and came across a problem when calculation ending WIP for equivalent units using the weighted average method.

    Kimbeth Manufacturing uses a process cost system to manufacture Dust Density Sensors for the mining industry. The following information pertains to operations for the month of May:

    Units

    Beginning work-in-process inventory, May 1

    16,000

    Started in production during May

    100,000

    Completed production during May

    92,000

    Ending work-in-process inventory, May 31

    24,000

    The beginning inventory was 60 percent complete for materials and 20 percent complete for conversion costs.

    The ending inventory was 90 percent complete for materials and 40 percent complete for conversion costs.

    Costs pertaining to the month of May are as follows:

    Beginning inventory costs are: materials, $54,560; direct labor $20,320; and factory overhead, $15,240.

    Costs incurred during May are: materials used, $468,000; direct labor, $182,880; and factory overhead, $391,160.

    Using the weighted-average method, the total cost of the units in the ending work-in-process inventory at May 31, 1995, is:

    a. $155,328

    b. $156,960

    c. $154,800

    d. $153,960

    The answer states B but the explanation gives no clue how they applied the weighted average and got the unit costs to get the amount. I know you calculate separately but I am stuck at the equivalent units of (Materials:21600, Conversion Costs 9600)

    #524880
    Anonymous
    Inactive

    Hello everyone. Im taking BEC in a couple of days and came across a problem when calculation ending WIP for equivalent units using the weighted average method.

    Kimbeth Manufacturing uses a process cost system to manufacture Dust Density Sensors for the mining industry. The following information pertains to operations for the month of May:

    Units

    Beginning work-in-process inventory, May 1

    16,000

    Started in production during May

    100,000

    Completed production during May

    92,000

    Ending work-in-process inventory, May 31

    24,000

    The beginning inventory was 60 percent complete for materials and 20 percent complete for conversion costs.

    The ending inventory was 90 percent complete for materials and 40 percent complete for conversion costs.

    Costs pertaining to the month of May are as follows:

    Beginning inventory costs are: materials, $54,560; direct labor $20,320; and factory overhead, $15,240.

    Costs incurred during May are: materials used, $468,000; direct labor, $182,880; and factory overhead, $391,160.

    Using the weighted-average method, the total cost of the units in the ending work-in-process inventory at May 31, 1995, is:

    a. $155,328

    b. $156,960

    c. $154,800

    d. $153,960

    The answer states B but the explanation gives no clue how they applied the weighted average and got the unit costs to get the amount. I know you calculate separately but I am stuck at the equivalent units of (Materials:21600, Conversion Costs 9600)

    #524824
    JustWant 75
    Member

    @dotaganza i think if you solve for the DM and Conversion cost (Labor + OH) separately, you will get the correct answer.

    Find the Equivalent units for DM and Conversion separately:

    DM: Completed 9,200 + Ending 21,600(24,000*.9) = 113,600

    Conversion: Completed 9,200 + Ending 9,600(24,000*.4)=101,600

    Then find the total cost for DM and Conversion cost separately:

    DM: $54,560 Beg cost +$468,000 Current Cost = $ 522,560

    Conversion: $20,320 Beg DL + $15,240 Beg OH+$182,880 Current DL + $391,160 Current OH =$609,600

    Solve for cost per equivalent:

    DM: (Total cost /Equivalent units) $ 522,560/113,600 = $4.60

    Conversion: (Total cost /Equivalent units)$609,600/101,600 = $6.00

    Now you can solve for total cost of units in ending inventory:

    DM: (Ending inventory * cost per equivalent unit) 21,600 * $4.60=$99,360

    Conversion: (Ending inventory * cost per equivalent unit) 9,600 * $6.00 =$57,600

    Total of DM and Conversion in ending inventory = $99,360+$57,600 =$156,960

    Hope this makes sense

    Becker, Ninja Audio + Notes

    FAR: 80 (Aug 2013)
    AUD: 91 (Nov 2013)
    BEC: 79 (Feb 2014)
    REG: 80 (May 2014)

    #524882
    JustWant 75
    Member

    @dotaganza i think if you solve for the DM and Conversion cost (Labor + OH) separately, you will get the correct answer.

    Find the Equivalent units for DM and Conversion separately:

    DM: Completed 9,200 + Ending 21,600(24,000*.9) = 113,600

    Conversion: Completed 9,200 + Ending 9,600(24,000*.4)=101,600

    Then find the total cost for DM and Conversion cost separately:

    DM: $54,560 Beg cost +$468,000 Current Cost = $ 522,560

    Conversion: $20,320 Beg DL + $15,240 Beg OH+$182,880 Current DL + $391,160 Current OH =$609,600

    Solve for cost per equivalent:

    DM: (Total cost /Equivalent units) $ 522,560/113,600 = $4.60

    Conversion: (Total cost /Equivalent units)$609,600/101,600 = $6.00

    Now you can solve for total cost of units in ending inventory:

    DM: (Ending inventory * cost per equivalent unit) 21,600 * $4.60=$99,360

    Conversion: (Ending inventory * cost per equivalent unit) 9,600 * $6.00 =$57,600

    Total of DM and Conversion in ending inventory = $99,360+$57,600 =$156,960

    Hope this makes sense

    Becker, Ninja Audio + Notes

    FAR: 80 (Aug 2013)
    AUD: 91 (Nov 2013)
    BEC: 79 (Feb 2014)
    REG: 80 (May 2014)

    #524826
    jw_83
    Member

    My 2nd attempt at the BEC exam is tomorrow. I went over budgeting this morning and cost accounting at lunch. I think I will just read over my notes this evening and go to be early. Then before the exam rewrite my formulas one last time. This is my last exam and I am so ready to be done!

    REG - 64, 72, 81!
    FAR - 77
    AUD - 79
    BEC - 72, 79! And Done!

    #524884
    jw_83
    Member

    My 2nd attempt at the BEC exam is tomorrow. I went over budgeting this morning and cost accounting at lunch. I think I will just read over my notes this evening and go to be early. Then before the exam rewrite my formulas one last time. This is my last exam and I am so ready to be done!

    REG - 64, 72, 81!
    FAR - 77
    AUD - 79
    BEC - 72, 79! And Done!

    #524828
    Anonymous
    Inactive

    This is my first time posting on this website although I have utilized this site for about two years now. I have BEC aas my last exam. But because of my lack of discipline I waited for the last minute. So, if I fail I will have to retake Reg. But this is not my concern due to my prodigious amount of confidence. So, now after my little background here is a question from Becker I am little confused with. What is the difference between the $8 standard variable OH cost and the $9 standard direct labor rate?

    I would post the whole question but I cannot copy and im too lazy to write word for word. But here is the necessary info……….

    They give a box with the “unit standard factory overhead costs” of variable (4 hours at $8 an hour) and fixed costs ($irrelevant).

    Then on the bottom they give “following additional info”:

    22,000 pumps prodcued although 25,000 is potential output

    94,000 direct labor hours worked at a total cost of $940,000

    Standard direct labor rate of $9 an hour

    standard direct labor time is 4 hours a unit

    variable oh costs incurred of $740,000

    FOH irrelevant

    They then ask for the variable oh efficiency variance……..

    The answer is $48,000 unfavorable which they use the $8 an hour rate. I understand there calculation but what I dont understand is what is the difference between the standard factory overhead variable cost of $8 and the standard direct labor rate of $9.

    Sorry for the long post……and appreciate your responses….

    Thanks

    #524886
    Anonymous
    Inactive

    This is my first time posting on this website although I have utilized this site for about two years now. I have BEC aas my last exam. But because of my lack of discipline I waited for the last minute. So, if I fail I will have to retake Reg. But this is not my concern due to my prodigious amount of confidence. So, now after my little background here is a question from Becker I am little confused with. What is the difference between the $8 standard variable OH cost and the $9 standard direct labor rate?

    I would post the whole question but I cannot copy and im too lazy to write word for word. But here is the necessary info……….

    They give a box with the “unit standard factory overhead costs” of variable (4 hours at $8 an hour) and fixed costs ($irrelevant).

    Then on the bottom they give “following additional info”:

    22,000 pumps prodcued although 25,000 is potential output

    94,000 direct labor hours worked at a total cost of $940,000

    Standard direct labor rate of $9 an hour

    standard direct labor time is 4 hours a unit

    variable oh costs incurred of $740,000

    FOH irrelevant

    They then ask for the variable oh efficiency variance……..

    The answer is $48,000 unfavorable which they use the $8 an hour rate. I understand there calculation but what I dont understand is what is the difference between the standard factory overhead variable cost of $8 and the standard direct labor rate of $9.

    Sorry for the long post……and appreciate your responses….

    Thanks

    #524830
    jeff
    Keymaster

    bump

    Jeff Elliott, CPA (KS) | Another71 | NINJA CPA | NINJA CMA | NINJA CPE

    #524888
    jeff
    Keymaster

    bump

    Jeff Elliott, CPA (KS) | Another71 | NINJA CPA | NINJA CMA | NINJA CPE

    #524831
    jpowell31
    Participant

    I was hoping you would get a response @Deozzman101. I have been redoing variance problems over and over and everytime I get to that one it throws me off completely. Now I know the answer so it's not helpful.. hoping this bump will encourage someone to help.

    I think I understand otherwise as well but it's not sticking so any clarification @Deozzman101 would help: the same info is provided for the spending variance and only the $9 is used…which is probably why you're confused as well. But also, how do we know whether to use the actual DL hours provided or the actual DL hours given the amount actually produced x 4 for the P/spending variance? My exam is Monday and I am determined to understand the variances completely by then!

    #524890
    jpowell31
    Participant

    I was hoping you would get a response @Deozzman101. I have been redoing variance problems over and over and everytime I get to that one it throws me off completely. Now I know the answer so it's not helpful.. hoping this bump will encourage someone to help.

    I think I understand otherwise as well but it's not sticking so any clarification @Deozzman101 would help: the same info is provided for the spending variance and only the $9 is used…which is probably why you're confused as well. But also, how do we know whether to use the actual DL hours provided or the actual DL hours given the amount actually produced x 4 for the P/spending variance? My exam is Monday and I am determined to understand the variances completely by then!

    #524834
    JustWant 75
    Member

    @Deozzman101 i'm not sure if i'm correct but when the question asks to solve for “variable OH”, i only use variable costs. When the question is asking for DL efficiency and rate variance, then i use the DL rate. @jpowell31, can you copy and paste the question if possible so i can take a look. I worked on a lot of variance MCQ's today and i feel like it's finally sticking.

    Becker, Ninja Audio + Notes

    FAR: 80 (Aug 2013)
    AUD: 91 (Nov 2013)
    BEC: 79 (Feb 2014)
    REG: 80 (May 2014)

    #524892
    JustWant 75
    Member

    @Deozzman101 i'm not sure if i'm correct but when the question asks to solve for “variable OH”, i only use variable costs. When the question is asking for DL efficiency and rate variance, then i use the DL rate. @jpowell31, can you copy and paste the question if possible so i can take a look. I worked on a lot of variance MCQ's today and i feel like it's finally sticking.

    Becker, Ninja Audio + Notes

    FAR: 80 (Aug 2013)
    AUD: 91 (Nov 2013)
    BEC: 79 (Feb 2014)
    REG: 80 (May 2014)

Viewing 15 replies - 316 through 330 (of 440 total)
  • The topic ‘[Q1] BEC Study Group 2014 - Page 22’ is closed to new replies.